Skip to main content

How do I submit Boots On Ground for a work order on the web?

Record who was on site, when and for how long: open Boots On Ground from a work order, check what's filled in, add crew and hours, and submit.

Open the work order, click + at the top and pick Boots On Ground. A panel opens on the right, already filled in from the job. Add the SAM ID, the supervisor, your crew size and hours, and the details your company asks for, then click Submit.

Boots On Ground (BOG) is the daily record of who was on site for a job, on which day and for how long. Submit one for each day you work on site. This guide is for field technicians and subcontractors working on the web.

1. Open the form from the work order

Open the work order and click + next to Download at the top, then Boots On Ground. The Create New Boots on Ground panel opens on the right, over the work order, so you don't lose your place.

The plus button on a work order is clicked, Boots On Ground is picked, and the Create New Boots on Ground panel opens on the right, filled in from the job.

For a few seconds the footer says Filling in from the work order… and the Job section says Loading work order…. Wait for them to finish before you type.

You can also start one from the Work Order list: open a job's Preview and use its + menu.

2. Find your way around the panel

The top of the Create New Boots on Ground panel, with the help button, the close button and Open full page.

  • The form is in sections: Visit, Job, Site address, Crew & hours and Additional details. Click a section's title to fold it away. A folded section still shows a one-line summary of what's in it.

  • A red badge such as 3 required tells you how many fields in that section still need an answer.

  • The note at the bottom says Please fill all mandatory fields. until everything required is done. Then it turns green, says Please click on Submit to submit BOG., and Submit can be clicked.

  • Open full page opens the same form on its own page if you want more room. The ? opens help for this form.

The panel footer saying Please fill all mandatory fields, with Cancel and a greyed-out Submit button.

3. Check the Visit and Job sections

Field

What to do

Logging for

Self if you're recording your own visit. For Someone else if you're recording it for another company's crew; you then pick their company in Construction Partner Company Name. If your login belongs to a subcontractor company, you don't see this choice: your company is filled in for you.

Date On-Site

Today, filled in for you. Change it if you're recording a different day. Your company decides how many days back or ahead you can pick.

Project, Site

Filled in from the work order.

SAM ID

Type the SAM ID for the job. Required.

Task Type, Job Code

Filled in from the work order. Click Job Code to pick or type a different one.

Your company can hide fields it doesn't use, so you may see fewer than this.

4. Check the site address

The address comes from the work order. To change it, start typing in Site Address and pick a suggestion. Street, City, State, Country and Post Code fill in from it.

The Site address section, filled in from the work order: Site Address, Street, City and State.

5. Add the crew and hours

The Crew and hours section with a 3 required badge: DP Field Supervisor, Crew Size, Work Hours and Total Hours.

  • DP Field Supervisor: pick the supervisor for the job. The list shows supervisors for the address's state, so check the state first. If no state is set, you see Select state first.

  • Crew Size: how many people were on site, including you.

  • Work Hours: how many hours each person worked.

  • Total Hours is worked out for you: crew size times work hours.

Crew Size 3 and Work Hours 8 are typed in the Crew and hours section, and Total Hours shows 24.

Total Hours updates when you leave the Work Hours box. If you change Crew Size afterwards, click into Work Hours and out again so the total catches up.

6. Fill in the additional details

Additional details holds your company's own questions, for example Program of Work, Estimated Start Time, Estimated Finish Time, Activity, Activity Type, Build Phase and Commentary. Questions marked * are required. The section shows Incomplete until they're answered.

The Additional details section: Estimated Start Time, Estimated Finish Time, Activity, Activity Type, Build Phase and Commentary.

7. Submit

When the note at the bottom turns green, click Submit. You see Boots on ground created successfully and the panel closes.

Cancel or the X closes the panel without saving. If you press Esc after typing something, a Discard changes? box asks first: Keep editing goes back to the form, Discard throws it away.

Common questions

Can I change a Boots On Ground after I submit it?

No. Only admins can edit a submitted one: you see Only admins can edit Boots on Ground. Ask your admin to correct it. You can delete one you submitted yourself from the Boots on Ground page in the left menu, and submit it again.

Why can't I pick the date I want?

Your company limits how many days back or ahead a Boots On Ground can be dated. Ask your admin if you need an older day.

Nothing happens when I pick Boots On Ground.

Your role isn't allowed to create them, and a message says so. Ask your admin.

Where do I see the ones I've submitted?

On the Boots on Ground page in the left menu. See How do I find, map and download Boots On Ground records on the web?.

Related articles

Did this answer your question?